Broad Run

Can build roughly 100,000 SF footprint.
Greenworks Assemblage

Data requires spex.
Clintmar Industrial Land

Recently aquired neighbors site to make this site much more usable.
Youngwood

Data development surrounding the parcel Exisiting leases valid through 2/26.
Virk Assemblage

Current site plan approved .6 FAR could be acheived with special exception.
Gainesville Business Park

Zoning allows data within data overlay. Expected to be added to overlay in 2024
Gainesville Assemblage

Zoning allows data within data overlay. Expected to be added to overlay in 2024
Comcast

Proffer amendment filed for increased FAR. Approval est. Q3/2023. Located within Data Center Overlay
ARC

Permanent power will require a
new substation to be built, which
will be 36-48 months.
Dulles Trade Center West

Application submitted to increase FAR to .6. Expected approval Q2 – 2023